Kolo Verify
House construction · Concrete and RCC structure checks

Cube samples taken and tested for this pour

By the Kolo house construction team · Updated

Why — act while you have leverage

The cube test is the only evidence of what strength you actually received. Without it, a weak pour is a matter of opinion, and the opinion that counts will be the contractor's.

What — examine the details

What to look at

  • Cubes cast in your presence, from the same concrete
  • Date and pour location marked on each cube
  • A lab report naming the mix and the 28-day result
  • 7-day cube test report
  • 28-day cube test report

Documents to ask for

  • 7-day cube test report
  • 28-day cube test report
How

How to check it yourself

Cubes are cast at the pour from the concrete going into the structure — not from a separately mixed batch — marked with the date and location, cured in water, and tested at 7 and 28 days by a lab. The 28-day report is the one that matters and belongs in your file.

Where this comes from: IS 456:2000 cl. 15 (acceptance criteria) and cl. 16; IS 516 (method of test) (indian standard or building code)

More concrete and rcc structure checks

The whole stage: Concrete and RCC structure checks

Chat with us