Shuttering not struck before the code minimum

By the Kolo house construction team · Updated

Why — act while you have leverage

Formwork (the mould the concrete is poured into) removed early is the most common cause of a slab that sags permanently. The concrete has not yet carried its own weight, and the deflection you get is the deflection you keep.

What — examine the details

What to look at

  • A dated record of when each element was poured
  • Props left in place, not removed and re-wedged
  • Longer periods where the span is larger
How

How to check it yourself

Stripping times run from the pour, and the code separates vertical faces from soffit (the underside — the ceiling of the room below)s and from props. Props under slabs and beams stay far longer than the side shutters — reading "shuttering (the mould the concrete is poured into) removed" as one event is the mistake.

Where this comes from: IS 456:2000 cl. 11.3 — stripping time; Table 11 (indian standard or building code)