Mortar used within its working time, and never re-tempered

By the Kolo house construction team · Updated

Why — act while you have leverage

Mortar that has started to set and is brought back with water has lost most of its strength. It looks identical to fresh mortar in the wall and is the reason joints in the last course of the day are often the weakest.

What — examine the details

What to look at

  • Batch sizes matched to the crew's pace, not to the mixer's capacity
  • Leftover mortar thrown away at the end of a session
  • No water hose kept beside the mortar board for softening
How

How to check it yourself

Mortar is mixed in quantities that can be used within its working time and what is left over is discarded, not revived. Reviving stiffened mortar with water — adding water to stiffened mortar to make it workable again — is the practice to watch for, usually at the end of a shift when nobody wants to waste a batch.

Where this comes from: IS 2250:1981 — preparation and use of masonry mortars; IS 269 / IS 8112 for cement setting times (indian standard or building code)