Why — act while you have leverage

Damp sand swells. Measure it by volume without allowing for that and you put far less sand in than you think — or, correcting the wrong way, far less cement. It is the most common reason a site that believes it is mixing 1:6 is not.

What — examine the details

What to look at

  • A bulking test done when the sand stack has been rained on
  • The gauge box count adjusted after rain rather than kept constant
  • Sand stored covered so its condition is at least consistent
How

How to check it yourself

Damp sand occupies noticeably more volume than the same sand dry — the effect is largest at low moisture, exactly the state sand is in on a covered stack after rain. The field test is simple: fill a container with damp sand, then saturate and settle it, and compare levels. Kerala sites in monsoon are the ones that most need it and least often do it.

Where this comes from: IS 2386 (Part 3) — Methods of test for aggregates, bulking of fine aggregate; IS 2250 for mortar proportioning (indian standard or building code)