Quote vs bill calculator
A quote is a list of assumptions. A low allowance for tiles, extras priced after work starts, and fittings the quote leaves out all reach the bill. Put in your own and see the gap between the quote and what you pay.
The figures filled in are the worked example from our article, not market rates. Change them to yours.
₹12.1 lakh between the quote and the bill.
| Tiles above the allowance | ₹5,10,000 |
|---|---|
| Extras, less what the lower quote saved | ₹2,00,000 |
| Fittings left out | ₹5,00,000 |
| Total | ₹12,10,000 |
(₹250 − ₹80) × 3,000 sq ft + (8 × ₹1,50,000 − ₹10,00,000) + ₹5,00,000 = ₹12,10,000
How it works
A low allowance costs the difference between what you want and what the quote allows, times the quantity. Extras cost their number times their average, less whatever the lower quote saved you. Items the quote leaves out are added as they are.
Why this happens
How to check it yourself
Have a Kolo expert look at it
Construction quotation check
One contractor quotation read line by line — what is priced, what is vague, what is missing.
- A plain reading of one quotation
- What it leaves out — the extras you would otherwise meet halfway through
- What to ask the contractor before you accept it
Analysis · ready in 3 working days
See Construction quotation check →Available for sites anywhere in India except Kerala.
Compare construction quotations
Quotes normalised to the same scope, so you compare prices — not guesses.
- Brands, grades and inclusions aligned so each line compares
Comparison sheet · ready in 5 working days
See Compare construction quotations →Available for sites anywhere in India except Kerala.