Why your quote isn't your price
A quote looks like a price, but it's really a list of assumptions. It's the number most of us plan our loan around, and three things make it move after you sign.
Every figure here is an example, with the arithmetic shown. Your own numbers will differ; the reasons won't.
₹3,500 a sq ft, for what?
A per sq ft rate is the first number most of us hear, and it feels easy to compare. But two contractors quoting ₹3,500 a sq ft are not quoting the same house.
The rate hides the specification: which steel brand, which cement grade, how much is allowed for tiles, doors and fittings. The contractor knows exactly what's inside that number. You see one figure, so you can't tell what's been left out until the bills arrive.
Say the quote allows ₹80 a sq ft for tiles, and the tiles you want cost ₹250. On 3,000 sq ft of flooring, that's ₹5.1 lakh more.
(₹250 − ₹80) × 3,000 sq ft = ₹5,10,000
Why the lowest quote can cost the most
Most of us pick the lowest number. It's the sensible thing to do with the information we have.
But think about how a contractor wins work. The lowest price gets the job. Once work starts, anything outside the quote becomes an extra, and extras are priced when you have no other option. Not every low quote works this way. The system just makes it pay to quote low and recover later.
Say one quote is ₹10 lakh lower on a ₹1.2 crore house. Then eight items come up as extras at about ₹1.5 lakh each. That's ₹12 lakh, so the cheaper quote ends up ₹2 lakh dearer.
−₹10 lakh saved + ₹12 lakh extras = ₹2 lakh more
Three quotes, three formats
You got three quotes. One is a single page. One is a 40-line list. One is a per sq ft rate with a few notes. You can't actually compare them.
Each contractor splits the work differently. One includes plumbing and electrical fittings, another leaves them out. One counts the staircase, another doesn't. To compare them, you'd have to rebuild all three into one format. That's a job even engineers find hard.
Say quote B leaves out ₹5 lakh of fittings that quote A includes. B looks ₹5 lakh cheaper. It's the same house.
Quote A ₹1.2 crore (fittings in) · Quote B ₹1.15 crore (fittings out) → the same house
What it adds up to
Say ₹5.1 lakh on tiles, ₹2 lakh net on extras and ₹5 lakh of missing fittings. That's ₹12.1 lakh between the quote and the bill.
₹5,10,000 + ₹2,00,000 + ₹5,00,000 = ₹12,10,000
What you can do
None of this is your fault. A quote is written by the person who knows what it leaves out.
The way through is to send every contractor the same specification and the same list of items, compare line by line, never total against total, and name what each quote leaves out before you choose.
How to check it yourself
Step by step in our guides: what to look at, and the law, code or practice behind it.
Have a Kolo expert look at it
Construction quotation check
One contractor quotation read line by line — what is priced, what is vague, what is missing.
- A plain reading of one quotation
- What it leaves out — the extras you would otherwise meet halfway through
- What to ask the contractor before you accept it
Analysis · ready in 3 working days
See Construction quotation check →Available for sites anywhere in India except Kerala.
Compare construction quotations
Quotes normalised to the same scope, so you compare prices — not guesses.
- Brands, grades and inclusions aligned so each line compares
Comparison sheet · ready in 5 working days
See Compare construction quotations →Available for sites anywhere in India except Kerala.
Material & brand check
Grades and thicknesses checked — so what is priced is what gets built.
- Lines vague enough to be downgraded on site
Audit · ready in 3 working days
See Material & brand check →Available for sites anywhere in India except Kerala.