Price escalation calculator

One line in a building contract — "rates subject to market variation" — decides who pays when material prices rise. Put in your steel, its price and a rise, and see what that line costs you, with and without a cap.

The figures filled in are the worked example from our article, not market rates. Change them to yours.

0 means no cap.

₹98,000 added by one line in your contract.

Steel at the signed price₹9,80,000
What the rise adds, uncapped₹98,000
What you pay with your cap₹98,000

14,000 kg × ₹70 = ₹9,80,000 · 10% rise = ₹98,000

How it works

The steel your house needs times its price is what it costs at the rate you signed. A rise in the price, as a percentage of that, is what an open escalation clause passes to you. A cap in the contract limits what you pay to the capped percentage.

The why

Why this happens

Why your building contract favours the other side

The how

How to check it yourself

Or let Kolo do it

Have a Kolo expert look at it

Construction agreement review

Your agreement read clause by clause, with the risks ranked before you sign.

  • Payment, retention, escalation, warranty, delay and arbitration clauses checked
  • With the full review: a payment schedule you can propose to the contractor

Risk report · ready in 5 working days

See Construction agreement review →

Available for sites anywhere in India except Kerala.

More calculators

Chat with us