Price escalation calculator
One line in a building contract — "rates subject to market variation" — decides who pays when material prices rise. Put in your steel, its price and a rise, and see what that line costs you, with and without a cap.
The figures filled in are the worked example from our article, not market rates. Change them to yours.
₹98,000 added by one line in your contract.
| Steel at the signed price | ₹9,80,000 |
|---|---|
| What the rise adds, uncapped | ₹98,000 |
| What you pay with your cap | ₹98,000 |
14,000 kg × ₹70 = ₹9,80,000 · 10% rise = ₹98,000
How it works
The steel your house needs times its price is what it costs at the rate you signed. A rise in the price, as a percentage of that, is what an open escalation clause passes to you. A cap in the contract limits what you pay to the capped percentage.
Why this happens
How to check it yourself
Have a Kolo expert look at it
Construction agreement review
Your agreement read clause by clause, with the risks ranked before you sign.
- Payment, retention, escalation, warranty, delay and arbitration clauses checked
- With the full review: a payment schedule you can propose to the contractor
Risk report · ready in 5 working days
See Construction agreement review →Available for sites anywhere in India except Kerala.