The payment schedule keeps money back until the end

By the Kolo house construction team · Updated

Why — act while you have leverage

Payment schedules are the part of an agreement most often written in the contractor's favour, and the least often read. Several released almost the whole contract before the house was finished - one left under one per cent for handover and every defect after it.

What — examine the details

What to look at

  • The milestone percentages adding to 100
  • What is left for handover and the defect period - Kerala practice is around 5%
  • The advance, and what it is secured against
  • A milestone for every trade you are paying for, including flooring and painting
How

How to check it yourself

Add the milestones up as percentages and look at two numbers: how much is due before any work starts, and how much is left at handover. Money paid ahead of verified work is leverage you no longer have. Then check the last milestone is tied to handover itself, not to plastering or to some stage before the finishes.

Where this comes from: Kolo review of Kerala construction quotations and agreements (established trade practice)