Kolo Verify
Why homeowners lose out · 6 of 6

Why your building contract favours the other side

By Jery, founder of Kolo · Updated

The contract decides who carries the risk when something changes, and it usually isn't the contractor. You sign it once, at the start, under time pressure. Here's what it decides for you, without anyone breaking a rule.

Every figure here is an example, with the arithmetic shown. Your own numbers will differ; the reasons won't.

Reason 1 · What they know that you don't

One line: "rates subject to market variation"

Your contractor has signed hundreds of contracts. You're signing your first. It arrives long, in legal language, with work due to start next week.

Your contractor knows which lines matter. Take one: "rates subject to market variation". It means that if steel or cement prices rise, you pay the difference. It reads like a formality. It's the line that decides who carries the price risk for the next year.

Say your house needs 14,000 kg of steel at ₹70 a kg. If the price rises 10% during the build, that one line adds ₹98,000.

14,000 kg × ₹70 = ₹9,80,000 · 10% rise = ₹98,000

Reason 2 · How they are paid

When payments run ahead of the work

Most schedules start with an advance, then payments by month or by stage. Look at yours and ask: who does it protect?

Money paid before the work is done changes who has leverage. Once a contractor is ahead on payments, finishing your house on time matters less to their cash flow than starting the next one. They're not being dishonest. They're running a business, and the schedule tells them where their money comes from.

Say you pay a 20% advance on a ₹1.2 crore contract. That's ₹24 lakh before a single foundation is dug.

20% of ₹1.2 crore = ₹24 lakh paid on day one

Reason 3 · Too much to line up

When your documents disagree

A building contract isn't one document. It's drawings, a list of items, specifications, a schedule and payment terms.

Each one is made by a different person at a different time, so they often disagree. The drawing shows thicker walls; the item list prices thinner ones. Unless the contract says which document wins, every mismatch becomes an argument on site.

Say the wall mismatch is worth ₹3 lakh across the house. Without a line that says which document wins, that's a dispute, not an answer.

Drawing: 9-inch walls · Item list: 6-inch walls · Gap: ₹3,00,000

What it adds up to

Say ₹98,000 from a steel price rise and ₹3 lakh from one mismatch. That's nearly ₹4 lakh, with ₹24 lakh already paid before work began.

₹98,000 + ₹3,00,000 = ₹3,98,000

Try it with your numbers

Price escalation calculator

What you can do

None of this is your fault. The contract is written by the side that has signed hundreds of them.

The time to change it is before you sign, while asking still costs nothing: cap the escalation, tie every payment to measured work, keep money back until handover, and say which document wins.

The how

How to check it yourself

Step by step in our guides: what to look at, and the law, code or practice behind it.

Or let Kolo do it

Have a Kolo expert look at it

Construction agreement review

Your agreement read clause by clause, with the risks ranked before you sign.

  • Payment, retention, escalation, warranty, delay and arbitration clauses checked
  • With the full review: a payment schedule you can propose to the contractor

Risk report · ready in 5 working days

See Construction agreement review →

Available for sites anywhere in India except Kerala.

About the author. Jery founded Kolo, which has worked with homeowners on over 3,000 homes, from the first architect meeting to handover.

More: why homeowners lose out

The whole series

Chat with us