Why your house costs more than the plan said

By Jery, founder of Kolo · Updated

Most of your budget is decided before anyone quotes, when the floor plan and the 3D views are approved. That's also when it starts to slip, for three reasons that have nothing to do with how careful you are.

Every figure here is an example, with the arithmetic shown. Your own numbers will differ; the reasons won't.

Reason 1 · What they know that you don't

The plan doesn't show what anything costs

Your house plan shows every room. It doesn't show what any of them will cost to build. You get a nice 3D view, you approve it, and that's when most of your budget gets decided.

An architect knows which features cost a lot to build: large spans, cantilevers, double-height rooms, a wall of glass. To you, they're part of a good picture. Nobody puts a price next to them, so you can't see the trade-off you're making.

Say one feature adds 300 sq ft of extra wall and glass at ₹4,000 a sq ft. That's ₹12 lakh, approved without a price on it.

300 sq ft × ₹4,000 = ₹12,00,000

Reason 2 · How they are paid

Nobody is paid to make your house smaller

As a plan is drawn, extra space creeps in: a wider corridor, a bigger staircase hall, a room you'll rarely use.

Everyone who works on your house earns more if it gets bigger. The architect's fee often grows with area or cost. The contractor's bill grows with every sq ft. No one in the process is paid to take space out. So unused space stays in the plan, and you pay to build it, finish it and maintain it.

Say the plan has 400 sq ft you won't really use, at ₹3,500 a sq ft to build. That's ₹14 lakh.

400 sq ft × ₹3,500 = ₹14,00,000

Reason 3 · Too much to line up

Everything is linked, so one change moves ten things

Before construction starts, you make hundreds of decisions: room sizes, windows, stairs, where the water tank goes. They're all linked.

A wider room needs a longer beam. A longer beam needs more steel and a deeper slab. That changes the structural drawing, the estimate and the timeline. And you're making these calls for the first time, often after the drawings are done.

Say you widen a bedroom by two feet after the structural drawings are final. For example, ₹1 lakh in redesign and extra steel, plus two weeks.

Wider room → longer beam → more steel → new drawings → ₹1,00,000 + 2 weeks

What it adds up to

Say one feature adds ₹12 lakh, unused space adds ₹14 lakh and one late change adds ₹1 lakh. That's ₹27 lakh before a single brick is laid.

₹12,00,000 + ₹14,00,000 + ₹1,00,000 = ₹27,00,000

What you can do

None of this means your architect did a bad job, and none of it is your fault. The plan is simply the stage where cost is decided and least visible.

The way through is to put a number next to the big features, question every sq ft you won't use, and freeze the plan before the structural drawings are made, so changes happen on paper while they're still cheap.

The how

How to check it yourself

Step by step in our guides: what to look at, and the law, code or practice behind it.

Or let Kolo do it

Have a Kolo expert look at it

House plan review

An independent read of your plan for space, light, flow and cost — before it is frozen.

  • Circulation, furniture fit, ventilation and orientation checked
  • Corridors, dead corners and oversized circulation measured, and what they cost to build
  • Changes you can hand to your architect

Review · ready in 5 working days

See House plan review →

Available for sites in Kerala.

Structural design check

A second structural engineer reads your design for safety and wasted steel.

  • Members that look under- or over-designed, with the reason

Report · ready in 5 working days

See Structural design check →

Available for sites in Kerala.

About the author. Jery founded Kolo, which has worked with homeowners on over 3,000 homes, from the first architect meeting to handover.

More: why homeowners lose out

The whole series

Chat with us