Curing is the contractor's job, in writing

By the Kolo house construction team · Updated

Why — act while you have leverage

Concrete gains most of its strength in the first two weeks and only if it is kept wet. Agreements that push curing onto the owner transfer the single cheapest thing that determines how strong the house is - and one did it while offering a fifteen-year structural guarantee.

What — examine the details

What to look at

  • Curing named, with the responsible party
  • A stated number of days
  • How it squares with any structural guarantee in the same document
How

How to check it yourself

Find who is responsible for curing. IS 456 requires the surface to be kept wet for at least seven days in ordinary cases. If the agreement makes it yours, understand you have taken on a daily site duty for a fortnight per pour - and ask how a structural guarantee survives it.

Where this comes from: IS 456:2000 cl. 13.5 - curing (indian standard or building code)